BASIC SERVICES SCHEMATIC DESIGN PHASE: - Meet with client to review operational program and/or design criteria to meet functional requirements. DESIGN DEVELOPMENT PHASE: - Upon approval of Schematic Design Phase, prepare large scale CAD drawings of food service equipment floor plans with equipment schedules. CONTRACT DOCUMENT PHASE: - Provide Contract Drawings (CAD) to include large scale food service equipment floor plans with equipment schedules, equipment details (sections/elevations), mechanical and electrical rough-in drawings (dimensioned if required) of equipment utility requirements, area floor drains, and electrical convenience outlets. BIDDING/CONTRACT AWARD PHASE: - Provide listing of Food Service Equipment Contractor for Client’s consideration. CONTRACT ADMINISTRATION PHASE: - Review and approve Contractor’s submittal data (food service equipment manuals, custom fabricated equipment shop drawings), and dimensioned mechanical and electrical rough-in drawings. ADDITIONAL SERVICES - Preparation of formal program of operations criteria.
- Design studies to establish spatial requirements and area relationships to meet requirements.
- Prepare small scale drawings of proposed food service floor plan(s) for review and approval.
- Prepare outline specifications of proposed equipment.
-Prepare brochure manuals of proposed equipment.
- Prepare itemized food service equipment cost estimate for budget approval.
-Necessary presentation meetings to meet project requirements.
- Coordinate our work with other members of Architectural/ Engineering Design Team.
- Prepare food service equipment specifications for bidding and negotiation purposes.
- Prepare itemized food service equipment cost estimate.
- Evaluate and approve requests for alternate brands and material.
- Prepare advisory aid in receiving and review food service equipment bid proposals.
- Respond to Contractor’s Requests for Information and field related problems.
- Necessary inspection visits of food service equipment installation to ensure compliance with contract Documents, preparing complete listings of all discrepancies.
- Feasibility studies.
- Prepare Complete Bid Package.
- Attend job progress meetings and preliminary inspections relative to the food service equipment installation.
- Demonstrate the use of the food service equipment.